At the board of supervisors meeting for Douglass Township, an update was given about the construction of the long-awaited emergency service building. The progress has been smooth despite delays due to weather and the shipping of supplies.
The interior of the fire and police sections is complete. The heating and electric systems have been installed and soon the drop ceiling tiles will be put in place.
There is still a lot going on outside. Residents will still see excavation and parking lot construction. The landscaping will begin within the next few weeks as spring approaches. "It's a work in progress. Please be patient with us," said Emergency Services Board Member Andrew Duncan.
It is anticipated that the building will be completed and in use by the middle or end of March. Significant thought has been put into the construction of this building. Efficient LED lighting, forced natural gas heating, and on-demand hot water has been installed. "We are using taxpayer money to build this," said Duncan, also chief of Gilbertsville Fire and Rescue. "It's important that we pay attention to detail."
In addition, the EMS board received approval for monthly meetings instead of quarterly. Duncan explained that the organization has taken a backseat due to the construction of the new building. The focus is on the best possible training and personnel to serve the township.
Gary Schmoltz, of the Gilbertsville Ambulance, gave an update on the work they have been doing in Douglass Township and several neighboring communities. They serve many different locations. Detailed printed reports are available in the lobby of the township building.
Sergeant Robert Evans, of the Douglass Township Police Department, informed the board and residents that Chief Barry Templin will be returning next week. Evans thanked the board and township for their graciousness towards him as he filled in for the chief. He stated that he learned a lot and it was a great experience. "We have worked together for a long time," Chairman Joshua Stouch said. "Thank you for the great job you have done over the last few months."
Township Manager Peter Hiryak informed the board that a resolution is required to apply for the MontCo 2040 Park Grant. The grant award is approximately $80,000 with a 20 percent match required from the township. However, the township has received $30,000 in private donations. The solicitor is reviewing the donations to ensure they can be utilized for the grant match.
The funds from the grant will be used for a complete overlay of the tennis courts, net posts, bicycle racks, trees and an updated recycling area in the park. The motion was unanimously approved to apply for the grant.
In addition, Hiryak informed the board that he met with resident Alex Brumwell in regard to his request for maps depicting floodplains and aerial views showing stormwater flow. Hiryak stated it was a good meeting and that the township will continue to address Brumwell's concerns.
An executive session was held before the start of the public meeting to discuss personnel matters. No decisions were made.